HYDERABAD: The Telangana Real Estate Regulatory Authority (TGRERA) has passed a series of orders against 17 real estate developers, directing them to refund homebuyers, register allotted plots, clear mortgage-related encumbrances, provide promised parking facilities and complete pending infrastructure works.
The cases involved residential layouts, apartment projects, villa developments and commercial properties. The Authority dealt with complaints relating to delayed registrations, unregistered projects, dishonoured refund cheques, incomplete amenities and violations of statutory obligations under the Real Estate (Regulation and Development) Act, 2016.
In one case, TGRERA upheld the rights of 38 members of the Elite BHEL Employees Housing Society and directed the landowner-promoter concerned to execute and register sale deeds for their allotted plots upon receipt of the outstanding sale consideration.
In a case involving Sand Stone Infra's Jaswitha Estates project at Shankarpally, the Authority directed the developer to refund ₹47 lakh. BVR Infra Developers was directed to refund ₹6.10 lakh, along with annual interest of 10.85 per cent, to a purchaser of Plot No. 91 in SV Electronic City-3.
In another case involving the same developer, concerning the SV Golden City-V project at Ramanuthala, TGRERA directed it to obtain final layout approval, clear encumbrances on Plot No. 97, measuring 212 square yards, and complete registration of the plot in favour of the purchaser.
In the Googee Satellite Township project at Nomula, Googee Properties was directed to refund the outstanding amount of ₹18.80 lakh to a purchaser within 60 days. In a separate case involving Nest Infra Developers' Rayan Enclave at Bibinagar, the Authority directed the promoter to refund a booking amount of ₹1 lakh within 15 days.
The Authority imposed a penalty of ₹57,735 on the respondents in a case concerning an unregistered plotted layout at Gurralapadu in Khammam.
In the case involving Ashritha's Group's Signature Towers at Thumkunta, the developer was directed to refund ₹9 lakh collected towards a flat booking within 60 days.
Sudheesha Constructions was directed to refund ₹10 lakh, with annual interest of 10.85 per cent, and pay a penalty of ₹8,24,585 in connection with its Sudheesha Dimple Valley project at Puppalaguda.
In the Kapil Business Park case, involving Kausalya Infra Projects and BVM Energy & Residency, the Authority allowed the complainant to withdraw from the commercial unit allotment and directed the developers to refund ₹24,64,259 within 60 days, without interest.
In the Sree Towers project at Gajularamaram, Sree Builders was directed to allot and hand over two cellar parking spaces. In another parking-related dispute involving Honer Aquantis at Gopanpally, Honer Developers was directed to provide one car parking space to the complainants within 60 days, in coordination with the Flat Owners' Association.
In the Ayyappa Sri Rasthu project at Siddipet, Ayyappa Builders was directed to rectify deficiencies in essential amenities, including the construction of a proper septic tank, completion of drainage pipelines and provision of generator backup for both blocks. The work must be completed within 60 days at the developer's expense.
The Authority also issued a stern warning to RSR Greenway Infra in connection with its Rocketry Villa Project at Pocharam, directing it not to advertise, market, book or sell villas or other units without obtaining mandatory RERA registration. The developer had collected ₹95.10 lakh from the complainants towards a villa without securing the necessary approvals.
In an execution petition against RDB Hyderabad Infrastructures concerning RDB Coconut Grove Apartment, TGRERA imposed a continuing penalty of ₹5.34 lakh.
Meanwhile, in the Parijatha Homes case, the Authority dismissed a buyer's refund claim, observing that the complainant continued to hold legal ownership of the plot under a registered sale deed and could not seek a refund while retaining ownership.